Update by Rachel Nelson
Hi everyone
Some of you may have noticed our team out on site on Wednesday this week with the piling contractor Bullivants. They have now submitted their design to Stantec and this will be incorporated into the overall plan.
We continue to work with NCC around the Application in Principle and the Environment Agency for the permit we need to work in the river and to maintain our environmental obligations.
I'm hopeful that we will be able to confirm a start date for the work and the program of works when we have our next public meeting which I think is being arranged for Friday 30th April.
Have a great weekend
Rachel