Update by Christine Taylor
Good morning,
What a lovely week of weather we are having?
I really hope the weather stays fine for the bank holiday! Adam as always is ahead of the game and has provided an update of this weeks progress and the planned work for next week.
This week -
- Roger Bulivant (pilers) are continuing pile casing install. Approx. 35% of casings expected to be drilled/installed by close of play Friday.
- The problematic compressor for piling exchanged on Monday morning. Progress has been much better since then.
- ESH ops continuing to clear arisings from pile operation.
- Access and tightness of site, continuing to restrict progress, this however is not impacting on the programme
Planned work for next week -
- Roger bulivant to continue with pile casing installation
- Esh gang in attendance to piles
- Esh to continue with remove of arisings from pile operations
Please do not hesitate to contact me if anyone requires any further information.
Have a wonderful Bank Holiday and I will be in touch next week.
Christine