Adam is back from his break, and keen to update us all on the progress of site.

This week the site team have:

  • Completed the rebar installation to capping Beam
  • Construction capping beam concrete shutters
  • Pour Capping Beam 
  • Strip capping Beam following concrete curing overnight

Planned works for next week:

  • Preparation for the rebuild of existing stone retaining wall at both end of site
  • Rebuild the stonework to existing retaining wall at both ends of site
  • The team will start to dig out for low level concrete beam, and backfill to rear of capping beam
  • Install the handrail edge protection to capping beam
  • Commence the weep hole installation to new retaining wall

I hope you all have a lovely weekend.

Christine

Please Login in order to comment on this update.

View all updates
Work in your Community

Work in a business that supports your community

At Northumbrian Water, we work to make a difference in your community.

Have you considered a career that can help you do the same?

As well as the teams you see working in your streets, we have people doing a wide range of jobs that support that work to deliver the best possible water and sewerage services across the North East.

You can find out more about careers with Northumbrian Water and check out the latest vacancies by following the link below.

www.nwl.co.uk/careers