As the site closes for the week, please allow us to update you on our progress, once again, as always, the information has been provided by our Adam..

Progress for this week:

  • Capping beam concrete works completed last week
  • They have dug out and prepared for the reinstatement works to existing stone retaining wall at either end of site
  • Installed safety handrails in preperation to dig out works for the lew level toe beam, at river water level
  • Commenced the rebuild of the stone retaining wall, stonework 

Planned works for next week:

  • Concrete fill to rear of new stonework at either end of site
  • Commence the backfill to the rear of capping beam
  • Commentce install of land drain/weep holes to new section of capping beam
  • One the weephole drainage has been installed, dig out at low level for the toe beam is to follow on

As always, we are here to help. If anyone wishes to discuss this work or any aspect of the site, please do not hesitate to contact us.

Have a lovely weekend, and stay safe.

Christine

Please Login in order to comment on this update.

View all updates
Work in your Community

Work in a business that supports your community

At Northumbrian Water, we work to make a difference in your community.

Have you considered a career that can help you do the same?

As well as the teams you see working in your streets, we have people doing a wide range of jobs that support that work to deliver the best possible water and sewerage services across the North East.

You can find out more about careers with Northumbrian Water and check out the latest vacancies by following the link below.

www.nwl.co.uk/careers