Update by Christine Taylor
Good afternoon,
As promised the lovely Adam has provided an update from site, which includes last weeks progress.
Last week:
- Existing stone retaining wall rebuild completed and concrete backfilled
- Rear of capping beam backfilled and land drain/weephole arrangement install
- Commenced dig to face of capping beam, to start works on the cladding facing works to the new retaining wall
- Reduce coffer dam wall height to 2 bags high
Planned works for this week:
- Continue with reduce level dig to new retaining wall face and commence puddle clay install to help prevent water ingress from the river
- Blind out the dig with a layer of concrete to start forming the low level toe beam
Planned works for next week:
- Diamond drilling of new piles to allow the new toe beam to be tied back
- Start to form rebar for toe beam
Over the next couple of weeks my colleague Becky Gartland will be providing the updates with the help of Adam.
Stay warm.
Christine