It's been a while since my last update..........
Jason and the team are on commissioning now and half way through...commissioning will be done by 17th November and then the 2 week proving period starts. We should be fully operational by the end of the first week in December then we commence decommissioning the existing works.
So great progress!
Don't forget if you want to ask anything about the project please feel free.