Update by Simon Bright
Hi
Vinnie and Bernie have had another productive week, the tank area has been backfilled, connections were made in and out of the tank and a manhole has been built. Next week we plan to install drainage along the connecting footpath from the tank area to Dene Close. The footpath will be closed from 39 to 42 Piper Road and we will need access off Dene Close.
Simon