Update by Sarah Jayne Parvin
Good afternoon,
we have successfully installed and backfilled the storage tank within the grass verge at Prince of Wales Close.
We mentioned in our last update, work on West Avenue was slightly delayed, we anticipate further delays partly due to locating an unexpected water main, which needed diverting to allow us to progress with our essential work. On top of this last week we uncovered a gas main which needed some attention from Northern Gas Networks, not to mentioned storm Francis last week. Taking all these factors into consideration, we are anticipating the road closure being extended into the back end of September and hope the road will reopen no later than the 25th September 2020.
We would like to apologise for any inconvenience this may cause you, if you need to discuss this please don’t hesitate to contact me via email SarahJayne.Vickers@JNBentley.co.uk or alternatively us the 'contact us' link at the top of this page.
Thanks
Sarah
Please Login in order to comment on this update.