RAINWISE SCHEME

Prudhoe

We are working together with the community to reduce the risk of future flooding in areas of Prudhoe through our Rainwise initiative.

Start Date

November, 2016

Estimated End Date

March, 2017

Contractor

NW, ESH

Update by Simon Bright

Hi

We have been delayed on our programme by a few days as there was concrete around the existing culvert which needed to be removed. As long as things go to plan and there are no other obsticles in our way we may be able to catch this lost time up. The manhole over the stream is almost built now and we are getting on well the the drainage along Castle Road.

Next week the drain run should be complete ready to start the new manhole at the end of our fencing next to the Rowan Grove Junction.

Simon

Please Login in order to comment on this update.

View all updates
Rate us

Rate us

We would love to hear your feed back on our community portal.

There was an error saving your answers. Please try again.

Saving your answers.
Please wait.

Your answers have been saved. Thankyou for giving us your feedback.

1. Do you feel that our Community Portal has helped to keep you informed about our work?

2. How likely is it that you would recommend our Community Portal to a friend or colleague?

3. How likely is it that you would recommend Northumbrian Water to a friend or colleague?

4. Do you have any suggestions to improve our Community Portal? Optional