Hi everyone
Things are picking up speed now.
Cockfield stw – Chemical bund is now complete and we are busy installing drainage around the Deep Bed Filter area
Ramshaw stw – Just installing the base reinforcement for the chemical bund and will shortly start constructing the backwash tank walls.
Butterknowle stw – We have justst completed excavating the Deep Bed Filter (DBF) slab and managed to install a new earth filter system to allow the backwash tank to be started.
Site traffic will be low. As always if you spot any issues let Brian know.
Many Thanks Martin