Update by Brian Hall
Hi
Just to give you an update on progress. We are still on programme to be completed in November. Our commissioning engineer is on site full time now and busy preparing plans ahead to allow the team to start bringing items of the new kit on line. Our civils contractor are still working hard to start completing areas to avoid delaying the trades ahead.
Thanks for the legacy suggestions that have been coming through since the update letter was sent out. We will let you know soon what our plans are going to be over the next few weeks.
Have a great weekend
Martin