Update by Brian Hall
Good afternoon
We have visited all three sites on the Gaunless with Northumbrian Waters Project engineer today to review progress. It is proving to be a challenge at present closing down the civil engineering work such as concreting and groundwork due to the constant rain but we are getting there. Electrical installation has progressed really well and we have been able to commission some of the new units to maintain our programme schedule. We will have our first delivery of chemicals on Monday at Cockfield, this will allow us to start closing down the projects and bringing down the phosphorus levels in the disharge water to meet the new Environment Agency standard. We will give you an update on how results are turning out over the next few weeks.
Have a great weekend.
Martin