Update by Brian Hall
Hi
The wet weather is causing us big problems across the 3 sites. At Butterknowle, Ramshaw and Cockfield the civil work is complete however we are unable to finish the landscaping works inside and out until areas dry up. We are going to monitor the weather and return at a suitable date. This will include upgrading the access track at Butterknowle.
Electrical and commissioning is proving to be a bit of a challenge at present therefore we will still be around for the next few weeks.
Will keep you informed with progress and a completion date soon.
Have a good weekend .
Thanks Martin