Update by Sarah Jayne Parvin
Good morning All, I would like to thank all of you for your patience and understanding over the last couple of months.
On Wednesday we had Flo, Northumbrian Water's customer vehicle at the end of Rookery Gardens and had the pleasure of seeing some old and new faces. We shared our new plans and the project headlines with you, please click Here to view the plan.
Our construction start date is the 30th October 2019 with construction completion on 19th December 2019.
We very much look forward to working with your community to deliver this project with minimal impact as possible.
If you didn't get chance to pop along we are more than happy to arrange a suitable time to come and discuss with you. Any question please comment below or alternatively use the contact us option at the top of the page.
Thanks
Sarah Vickers
MMB Customer Liaison Officer.