Update by Steve Boyd (Project Manager)
Hi everyone,
To keep you updated, our works are now complete on Newton Road, the two way traffic signal controls are to be removed at approx 3.00pm this afternoon.
Works on site are going very well at present, we have completed the 375 diameter underground trenchless drainage from our drive pit out into the manhole within the highway on Newton Road as above.
The new drainage network installation on site, within Cleveland Lodge are also going well, having installed 375 and 750 diameter concrete drainage along with the construction of new manholes from the first of our drive pits towards our second adjacent to Farm Garth, these works shall continue into next week.
The second of our underground trenchless works within the site curtilage heading towards the green belt adjacent to Farm Garth has also gone well this week with the pilot rods being accepted within the reception pit on Wednesday of this week, and we have further continued with the smaller auger boring works in preparation for the 750 diameter next week.
I've attached a few photo's of the works
Have a nice weekend
Steve.