Update by Anthony Birkett
Hi Everyone
Thanks to Darren who has provided the information for this update:
This week, we have continued with the excavation of the new basin and it is currently around 80% complete. Next week we will start installing the associated drainage before we put down the topsoil and seed, which will start the following week.
We have managed to retain and reuse most of the excavated material from the basin to reprofile part of the land within the grounds of Cleveland Lodge. This equates to approximately 200 wagon loads which would have otherwise been taken off site and disposed of.
Work is also progressing well in the grass verge in Farm Garth where we are installing the large diameter drainage pipes. We expect this work to reach Roseberry Crescent at some point next week and the rolling road closure will begin heading towards Newton Road. As we near the road, it is likely that we will start to encounter various underground services so this may slow our progress a little.
I've attached a couple of photos of the new basin.
Have a nice weekend
Tony