Update by Anthony Birkett
Hi Everyone
I've been on site a bit this week, you may have seen me out and about. I have spent some time with Scott and the site team and then notified those affected by our next change. Next week we will start on the drainage in the junction of Headlam View and Rosehill Road. The will result in two way traffic lights for up to two weeks. We had expected to start this stage of the works on Monday 16 September 2019, but this will now commence on Wednesday 18 September 2019.
I've attached a couple of photos showing the location of our work. We will be working between the two manholes visible in the road.
Please take care around the traffic lights.
Regards
Tony