The construction phase of this project is now complete.

There may still be updates, so the project will remain here. We are still monitoring the project and will reply to any comments. So if you have any questions please feel free to comment or contact us here.

GENERAL PROJECT

Ryhope Service Reservoir Refurbishment

Maintenance works are being carried out to the service reservoir located on the grounds of the Ryhope Pumping Station. This is an underground tank and works will be completed to both the outside and inside of the structure to ensure the supplies of Water coming from this asset are kept to the highest standard for years to come.

Update by Callum McCormack

Hi all, this week has flown by and we are still making good progress. The soil removal from the roof is now complete and we have now removed half the soil from around the roof (trench) and one half the of cleared roof has now been cleaned using the jet wash as you can see in the video. Any questions, please do shout..

Please Login in order to comment on this update.

View all updates
Work in your Community

Work in a business that supports your community

At Northumbrian Water, we work to make a difference in your community.

Have you considered a career that can help you do the same?

As well as the teams you see working in your streets, we have people doing a wide range of jobs that support that work to deliver the best possible water and sewerage services across the North East.

You can find out more about careers with Northumbrian Water and check out the latest vacancies by following the link below.

www.nwl.co.uk/careers