GENERAL PROJECT

Sharpness Point Rising Main

Working with our framework partners, Esh-Stantec, Northumbrian water will be carrying out work to replace a failing pumping main from Sharpness Point Pumping Station to Percy Park, Tynemouth.

Update by Rachel Rutter

Good Afternoon All, 

As our work continues I wanted to let you know the changes that have currently been made based on the feedback received.  We have been able to widen the footpath from 1.2 metres to 2 metres and new signage has been put in place to help with businesses. 

Our site team have also used a solar pod which is giving us 90% of our power on sunny days, as we continue to be mindful of our carbon footprint. 

The team were delayed by one day due to a concrete obstruction in the ground, they were able to use a specialist concrete cutting contractor to remove the concrete in sections to avoid damage to existing utility’s. Due to this we will be excavating and laying the new pipe as planned. 

Should you have any questions please email me on NWL.Customer@esh.uk.com.

Thank you 

Rachel 

Please Login in order to comment on this update.

View all updates
Work in your Community

Work in a business that supports your community

At Northumbrian Water, we work to make a difference in your community.

Have you considered a career that can help you do the same?

As well as the teams you see working in your streets, we have people doing a wide range of jobs that support that work to deliver the best possible water and sewerage services across the North East.

You can find out more about careers with Northumbrian Water and check out the latest vacancies by following the link below.

www.nwl.co.uk/careers