GENERAL PROJECT
CURRENT WEATHER
10°C

Stokesley and Great Ayton

We are investing £3.3 million to improve the performance of our wastewater treatment works in Stokesley and Great Ayton. We plan to begin this scheme in August 2018 and expect it will take up to 12 months to complete. This scheme will help to improve the water quality of the River Leven. Our partner, Interserve Construction Limited, will be carrying out this work on our behalf. Upgrades to the existing treatment works as well as the construction of new equipment at the two sites will be carried out. The construction works at both sites will be within the existing site boundaries, which are securely fenced off and our working hours are between 7.30am and 5.30pm, Monday to Friday. Construction traffic will need to access to the works from the A172 and A173, as a result, there will be a higher volume of site traffic when vehicles transport materials to and from the site. We will add drawings and photographs of similar works to this community portal to aid your understanding of the proposed works. We will also use the community portal to provide regular updates on the progress of the works once they commence. We would really like to hear any comments or questions you may have, so please get in touch using the 'Contact us' button at the top of the page or leave a comment below. Dean Thompson NWL project manager

Project updates

Update by Brian Hall

Hello everyone for information the construction of the Tertiary Treatment Plant was delayed by a few days to accommodate Social Distancing restrictions for the workforce. The Plant is due to be commissioned on the 7th April with the bulk of the construction works being completed by 9th April.

Non-essential activities will be resume once the Covid-19 restrictions have been lifted

 

Please Login in order to comment on this update.

Update by Brian Hall

Northumbrian Water need to undertake some additional works at Great Ayton Sewage Treatment Works to ensure that we can reliably achieve the new consent standard that has been set by the Environment Agency. This will mean that additional construction works will be taking place on site between Monday 24th February and Friday 3rd April. If you would like to discuss these additional works then please feel free to get in touch.

Dean Thompson NWL Project Manager

 

Please Login in order to comment on this update.

Update by Brian Hall

Hello everyone

Just a quick update on the work recently carried out.

We pleased to say that we are now complete at Stokesley Sewage Treatment Works and achieving the new consent. Landscaping and commissioning at Great Ayton is in the final stages. We are close to reaching the consent levels there also. Looking to be completed in the next few weeks.

 

Martin

 

Please Login in order to comment on this update.

Update by Brian Hall

 

Hello everyone

Hope you are all enjoying the hot weather. It has been a huge help to us to allow us to finish off areas. We are heavily into the commissioning stage on both sites now and everything is going well. We are leaving the speed restriction signs in place for a bit longer at Great Ayton STW so please be careful when driving in that area.

Martin

 

 

Please Login in order to comment on this update.

Update by Brian Hall

Hello everyone,

Another busy week at both sites, we were glad to see the weather improve after all the rain!

Great Ayton

We have installed the humus tank scraper bridge and completed the footpath, we are now begining site reinstatement works to get everything smart and back to working order

At Stokesley the mechanical electrical work is still ongoing

Have a great weekend everyone

 

Please Login in order to comment on this update.

Update by Brian Hall

Hi

At Great Ayton Sewage Treatment Works the team have had a successful week carrying out critical tie ins.  Northumbrian Water and the framework partners worked really well together to allow this to happen. This now allows reinstatement of areas to be carried out.

Sheet piles around the new humus tank are now removed and backfill is almost done. Footpaths to construct next.

At Stokesley Sewage Treatment Works the civil Construction work is now complete. Our commissioning department are now busy making everything work.

 

Enjoy the Bank Holiday weekend

 

Thanks

Please Login in order to comment on this update.

Update by Brian Hall

Hello everyone

We are about to remove sheet piles at Great Ayton Sewage Treatment Works now that the tank construction is complete. You may hear some banging noises as this progresses. We expect the work to run into next week. I

Please bear with us during this period.

 

Please Login in order to comment on this update.

Update by Brian Hall

Hello everyone

A busy few weeks at Great Ayton

The humus tank construction is well advanced; the radius walls are all complete as is the launder channel, the internal scaffolding has been removed to install benching. We will be removing the sheet pile and start backfilling around the tank this week.

The distribution chamber and the de-sludge chamber are now complete, we will be connecting next week as well as finishing ducting and pulling electrical cables through. There will be more reinstatement work going on this week; painting the bund and recasting the concrete slabs around it.

 

Please Login in order to comment on this update.

Update by Brian Hall

Good afternoon everyone, progress on both sites going well;

Great Ayton:

Humus tank wall construction ongoing

The Point Of Application slabs have been constructed

Delivery area construction is ongoing with sleeping policeman speed bumps being formed

Desludge chamber connection works ongoing

Ducting installation progressing site wide

Stokesley:

Chemical dosing commissioning has commenced

Electrical installation is complete

Prep and pouring of delivery area slabs ongoing

Lagging and trace heating installation for de-sludge pumps commenced

Have a great weekend everyone

 

Please Login in order to comment on this update.

Update by Brian Hall

Hi everyone,

Another busy week on both sites:

Great Ayton:

The Humus tank wall construction is ongoing

The Motor Control Centre (MCC) dosing slab has been constructed

The Delivery area construction is ongoing

Desludge chamber installation is ongoing

Stokesley:

Chemical dosing installation is ongoing

Electrical installation is ongoing

Preparation and pouring of delivery area concrete slabs are ongoing

The Primary Settlement Tank panel modification installation is ongoing

Lots more planned for next week. Brian

 

Please Login in order to comment on this update.

Work in your Community

Work in a business that supports your community

At Northumbrian Water, we work to make a difference in your community.

Have you considered a career that can help you do the same?

As well as the teams you see working in your streets, we have people doing a wide range of jobs that support that work to deliver the best possible water and sewerage services across the North East.

You can find out more about careers with Northumbrian Water and check out the latest vacancies by following the link below.

www.nwl.co.uk/careers