GENERAL PROJECT
CURRENT WEATHER
12°C

Stokesley and Great Ayton

We are investing £3.3 million to improve the performance of our wastewater treatment works in Stokesley and Great Ayton. We plan to begin this scheme in August 2018 and expect it will take up to 12 months to complete. This scheme will help to improve the water quality of the River Leven. Our partner, Interserve Construction Limited, will be carrying out this work on our behalf. Upgrades to the existing treatment works as well as the construction of new equipment at the two sites will be carried out. The construction works at both sites will be within the existing site boundaries, which are securely fenced off and our working hours are between 7.30am and 5.30pm, Monday to Friday. Construction traffic will need to access to the works from the A172 and A173, as a result, there will be a higher volume of site traffic when vehicles transport materials to and from the site. We will add drawings and photographs of similar works to this community portal to aid your understanding of the proposed works. We will also use the community portal to provide regular updates on the progress of the works once they commence. We would really like to hear any comments or questions you may have, so please get in touch using the 'Contact us' button at the top of the page or leave a comment below. Dean Thompson NWL project manager

Project updates

Update by Brian Hall

Good afternoon everyone, progress on both sites going well;

Great Ayton:

Humus tank wall construction ongoing

The Point Of Application slabs have been constructed

Delivery area construction is ongoing with sleeping policeman speed bumps being formed

Desludge chamber connection works ongoing

Ducting installation progressing site wide

Stokesley:

Chemical dosing commissioning has commenced

Electrical installation is complete

Prep and pouring of delivery area slabs ongoing

Lagging and trace heating installation for de-sludge pumps commenced

Have a great weekend everyone

 

Please Login in order to comment on this update.

Update by Brian Hall

Hi everyone,

Another busy week on both sites:

Great Ayton:

The Humus tank wall construction is ongoing

The Motor Control Centre (MCC) dosing slab has been constructed

The Delivery area construction is ongoing

Desludge chamber installation is ongoing

Stokesley:

Chemical dosing installation is ongoing

Electrical installation is ongoing

Preparation and pouring of delivery area concrete slabs are ongoing

The Primary Settlement Tank panel modification installation is ongoing

Lots more planned for next week. Brian

 

Please Login in order to comment on this update.

Update by Brian Hall

Hello everyone

I hope you are all enjoying the unseasonably warm weather.  Whatever you think of it,  the dry conditions are helping us crack on with work. Lots happening at both sites:

Great Ayton:

·         Humus tank wall construction ongoing

·         Chemical storage bund civils work complete

·         MCC dosing slab work ongoing

·         Delivery area construction ongoing

·         Desludge chamber installation ongoing

 

Stokesley:

·         Chemical dosing installation is ongoing

·         Electrical installation is ongoing

·         Prep work for the delivery area slab construction ongoing

Mopre updates soon

Brian

 

Please Login in order to comment on this update.

Update by Brian Hall

Hello everyone, just have a quick update of progress at Great Ayton and Stokesley sites:

Great Ayton:

  • Humus tank wall construction has commenced
  • Wall construction on chemical storage bund complete
  • MCC dosing slab work is ongoing
  • Delivery area construction has commenced
  • Desludge chamber installation is ongoing with removal of groundwork support

Stokesley:

  • Additional ducting has been installed
  • Chemical dosing installation is ongoing
  • Electrical installation is onging
  • Prep work for the delivery area slab is ongoing with ducts and drainage being installed

Brian

 

Please Login in order to comment on this update.

Update by Brian Hall

Hello all, work is progressing well over the past week at both sites:

Great Ayton:

Prep work for the humus tank base is almost complete, the wall kicker was set up for the base pour which we will be doing this week.

The installation of excavation support for the desludge chamber has commenced, the formation level has been excavated with base concrete due to be laid.

The chemical storage bund lower walls are concreted, leaving 1 remaining wall to construct to complete the FRC works to the bund.

Stokesley:

Chemical dosing installation is ongoing

Site wide electrical installation is ongoing

Works are ongoing on installing below slab ductwork and drainage below the new delivery area slab

Please Login in order to comment on this update.

Update by Brian Hall

Hello everyone

Work continues to go well at both sites

At Great Ayton; Pecafil has been installed to act as a form for the base concrete in the humus tank and chemical storage bund FRC works are ongoing.

At Stokesley the site ducting installation is complete, the sludge tank modifications are mechanically complete, and Chemical dosing and electrical installation is ongoing. Works have commenced on installing below slab ductwork and drainage below the new delivery area slab.

 

Please Login in order to comment on this update.

Update by Brian Hall

Hi everyone, again a busy week with lots going on at both sites

At Great Ayton:

Access has been improved into the humus tank and works ongoing reinforcing the base

Chemical storage bund wall construction is ongoing

At Stokesley:

Chemical dosing installation is ongoing

Electrical installation of the PST de-sludge pumps has commenced and are due to complete this week

Site wide ducting installation is now complete

All point of application kiosk bases have been constructed with kiosks landed in position

Sludge tank was emptied and cleaned allowing the new sludge mixing system to be installed this week

Please Login in order to comment on this update.

Update by Brian Hall

Hello everyone, work is progressing well on both sites. See below for a short summary:

Great Ayton:

Works on the chemical storage bund are progressing, the first bund wall has been concreted, and both of the octagonal plinths were concreted.  Wall construction is ongoing with another 4 wall pours remaining. Rebar installation is ongoing for the humus tank base, this is nearing completion with wall starter bars due to be installed.

Stokesley:

The chemical storage tanks were delivered and installed within the chemical storage bund. Site ducting installation is nearing completion, and the isolated chemical dosing point of application kiosk bases are underway and progressing well.

Please Login in order to comment on this update.

Update by Brian Hall

Hello everyone

We are all back to work at both sites and busy since the Christmas break, lots of work done at both sites; briefly:

Great Ayton:

Low level pipework for the humus tank was installed, testing of the pipework was successfull allowing the pipes to be concreted into position.

Rebar installation commenced for the humus tank base slab.

Formwork was installed on the chemical storage bund walls in readiness for a pour early next week.

Stokesley:

Site ducting installation continued after the road slabs were cut before Christmas.

The MCC base slab was set up and concreted in readiness for Sheers MCC dosing kiosk installation

 

 

Please Login in order to comment on this update.

Update by Brian Hall

We are ceasing work now until 7th January when we return to site. We would like to wish all our customers a Merry Christmas

 

Please Login in order to comment on this update.

Work in your Community

Work in a business that supports your community

At Northumbrian Water, we work to make a difference in your community.

Have you considered a career that can help you do the same?

As well as the teams you see working in your streets, we have people doing a wide range of jobs that support that work to deliver the best possible water and sewerage services across the North East.

You can find out more about careers with Northumbrian Water and check out the latest vacancies by following the link below.

www.nwl.co.uk/careers