Update by Brian Hall
Hi everyone
Just a quick update on work done this week at sites:
Great Ayton:
The installation of the sheet piles and frame for the cofferdam are complete. We will be transporting the excavated spoil off site commencing next week.
Stokesley:
The chemical storage bund base slab was poured, with rebar install to the walls commencing.
Northern Power Grid ducting was installed and the new REC kiosk slab was concreted this week in readiness for Northern Power Grids power upgrade.
The Primary Settlement Tank modifications commenced this week with the old pumps, pipework and flooring being stripped out in readiness for new slabs being cast next week.