Update by Brian Hall
Hello everyone a quick summary of last weeks progress is below with pictures attached:
Great Ayton: The chamber rings for the humus tank cone were installed and concreted into position. Steel fixing on the base of the cone commenced. The chemical storage bund base formwork was completed allowing the base to be concreted.
Stokesley: Two walls were concreted on the chemical storage bund. Pipework and pumps were installed on the PST chamber upgrades. Northern Power Grid successfully upgraded the power on site.