Update by Brian Hall
Hello everyone
We are all back to work at both sites and busy since the Christmas break, lots of work done at both sites; briefly:
Great Ayton:
Low level pipework for the humus tank was installed, testing of the pipework was successfull allowing the pipes to be concreted into position.
Rebar installation commenced for the humus tank base slab.
Formwork was installed on the chemical storage bund walls in readiness for a pour early next week.
Stokesley:
Site ducting installation continued after the road slabs were cut before Christmas.
The MCC base slab was set up and concreted in readiness for Sheers MCC dosing kiosk installation