Update by Brian Hall
Hello everyone
Work continues to go well at both sites
At Great Ayton; Pecafil has been installed to act as a form for the base concrete in the humus tank and chemical storage bund FRC works are ongoing.
At Stokesley the site ducting installation is complete, the sludge tank modifications are mechanically complete, and Chemical dosing and electrical installation is ongoing. Works have commenced on installing below slab ductwork and drainage below the new delivery area slab.