Update by Brian Hall
Hello all, work is progressing well over the past week at both sites:
Great Ayton:
Prep work for the humus tank base is almost complete, the wall kicker was set up for the base pour which we will be doing this week.
The installation of excavation support for the desludge chamber has commenced, the formation level has been excavated with base concrete due to be laid.
The chemical storage bund lower walls are concreted, leaving 1 remaining wall to construct to complete the FRC works to the bund.
Stokesley:
Chemical dosing installation is ongoing
Site wide electrical installation is ongoing
Works are ongoing on installing below slab ductwork and drainage below the new delivery area slab