Hello everyone, just have a quick update of progress at Great Ayton and Stokesley sites:
Great Ayton:
- Humus tank wall construction has commenced
- Wall construction on chemical storage bund complete
- MCC dosing slab work is ongoing
- Delivery area construction has commenced
- Desludge chamber installation is ongoing with removal of groundwork support
Stokesley:
- Additional ducting has been installed
- Chemical dosing installation is ongoing
- Electrical installation is onging
- Prep work for the delivery area slab is ongoing with ducts and drainage being installed
Brian