Update by Brian Hall
Hi everyone,
Another busy week on both sites:
Great Ayton:
The Humus tank wall construction is ongoing
The Motor Control Centre (MCC) dosing slab has been constructed
The Delivery area construction is ongoing
Desludge chamber installation is ongoing
Stokesley:
Chemical dosing installation is ongoing
Electrical installation is ongoing
Preparation and pouring of delivery area concrete slabs are ongoing
The Primary Settlement Tank panel modification installation is ongoing
Lots more planned for next week. Brian