Good afternoon everyone, progress on both sites going well;
Great Ayton:
Humus tank wall construction ongoing
The Point Of Application slabs have been constructed
Delivery area construction is ongoing with sleeping policeman speed bumps being formed
Desludge chamber connection works ongoing
Ducting installation progressing site wide
Stokesley:
Chemical dosing commissioning has commenced
Electrical installation is complete
Prep and pouring of delivery area slabs ongoing
Lagging and trace heating installation for de-sludge pumps commenced
Have a great weekend everyone