Update by Christine Taylor
Good afternoon
Please see below an update from the team on site.
Excavation was dug to proposed formation, it was found that there was an organic layer of material which needed to be removed. This resulted in a slight delay as a review of our current works design with regards to working methods, it has now been revised to allow us to excavate to a greater depth than originally anticipated and remove the organic layer of material. We have now started backfilling with a granular material to allow us to commence construction of the concrete structure from next week.
Christine