Update by Rachel Rutter
Good Afternoon All,
Hope you had a lovely weekend
The tertiary treatment plant and access steelwork has now been delivered to site and installed.
Over the next couple of weeks the team will be installing the interconnecting pipework and carrying out the electrical installation to the new tertiary treatment plant. Our civil works to the perimeter of the new structure will also be ongoing.
If you have any queries at all regarding our work in your area, please do not hesitate to contact us.