Update by Mark Robinson
Good Morning,
I visited site this morning and our team have commenced works to the final trial holes along Farringdon Row. We've moved North of the B & Q delivery entrance now, allowing access to both here and the retail paIk. Anyone wishing to access the Kings Arms pub or Timber Supplies needs to do so via Beach St.
We started with saw cutting and breaking up of the tarmac this morning and will progress with hand digging for the next few days to see what lies beneath.
I'll be in touch over the next couple of days with traffic updates for the next work area, along Deptford Terrace.
Mark