It’s time for another fortnightly update on SSTC Ph3
Farringdon Row.
All works are complete on Farringdon Row with the exception of 3 small patches of footpath. We hope to get these polished off in the next 2 weeks so we can remove our remaining fencing. I don’t expect these to cause any major inconvenience.
Hannover Place.
The main works on Hannover place are complete and we have been carrying out the connections to the various businesses this week. There is a short section of road outside the Hannover Place public house with a lane closure under two-way lights to facilitate one of the connections and some excavations in the footpaths for the rest.
All connections have now been completed and reinstatement will take place over the next few days to allow the lane to be reopened and the fencing to be removed.
The cobbled and footpath area outside the timber yard has now been reinstated and reopened though there will be another visit to this area next year.
Liebherr
NGN have started works outside Liebherr in the cobbled area to divert the gas main. Once this works is complete, we can look at our water main works, but I have no estimates at this time.
Deptford Terrace
The extra works here have been completed and excavations outside the Bus Depot and the Saltgrass public house have been reinstated. There may be some small visits in the future to carry out permanent reinstatement where the road surface is currently temporary.
Thanks for your on-going patience and please look through the photos attached.
Dave Eden