Update by Dave Eden
Morning everyone,
Time for another update on SSTC Phase 3:
Hannover Place
All works complete with the exception of one connection in the footpath between Hannover Place Pub and Liebherr plus some final reinstatement of the road and footpath.
Deptford Place
All works complete bar one customer connection which can be seen fenced off outside the Liebherr access plus some final footpath reinstatements. Due to issues with some other services clashing with NWGs water main this area is on hold until we design a solution. No work major expected until the new year.
Farringdon Row
All Works complete bar some surface box removal - fire hydrant covers and the like - plus some final footpath reinstatements.
Beech Street
Works starting in the new year to improve the water main. This will be done using pipe lining rather than opening a long trench so disruption will be kept to a minimum though some excavation will be required
We aren't expecting to do any major works in any of the above areas until into the new year with the possible exception of reinstating footpaths. I'll take a pause from these 2 weekly updates for the time being as I don't expect there to be any changes until into the new year but rest assured I will let you know as soon as there is.
We do have continuing works on the water mains within the main road contract however updates on those area are the responsibility of the principle contractor - Just because you don't see updates here does not mean we aren't working.
Thanks
Dave Eden