Tyneside Water Main Cleaning

Our water mains cleaning programme of works has been ongoing now for five years and to date, we have achieved 221km of cleaning works to our mains. There are a number of pipe sections that we still need to clean, with a total length of 9.0km. We are starting this work in August 2018 and anticipate completion in the Apri 2021.

Update by Katie Burdon

Trunks mains update

Glasshouse Bridge

Friday 7th September – Site meeting to discuss camera operation.

Met with Chris Donaldson the building maintenance manager from Newcastle Council Enterprise Centre who provisionally gave permission to undertake work on 15th - 18th September suspending and utilising 7 parking bays within the grounds.

Sunday 9th September

Churchill Street, Wallsend

Cut & cap the link main off 15” cast iron main and install washout. This now isolates the 15” main for abandonment. The outstanding works are the removal of 2x Air valve lids and frames and 1x valve lid all with backfill and reinstatement.

Monday 10th September

Fastflow completed 130m x 90mm HPPE open cut at Robinson Street/Corbridge Street/Headlam Street. Mains were pressure tested, chlorinated and sampled with the intention of undertaking x2 ITS’s on Tuesday 18th September at 10.30am and 11.30am to make the final connections. Backfill and reinstating is currently being undertaken.

Monday 10th/Tuesday 11th September

Fastflow started to prepare the excavation for the installation of a 300mm valve at the junction of Denmark Street and Heaton Road. This allows NWL to be able to control the water supplies in the Heaton area for future work.

Wednesday 12th September

Finish preparations for the 90mm HPPE connections on Heaton Road.

Thursday 13th September

At the junction of Denmark Street and Heaton Road a nightshift was undertaken from 23.00hrs with NWL isolating a 300mm water main and Fastflow installed a 300mm inline valve. (Photographs included)

Saturday 15th/Sunday 16th September

Glasshouse Bridge excavation will be undertaken on 30” water main in the car park of Newcastle Quayside Enterprise Centre, to locate and identify the 30” water main for the purpose of extracting a dowel and installing a camera to video the internal section of the main. This information will be scrutinised to determine a proposed technique of renewing the water main. The camera operation will be undertaken on Tuesday 18th September and the excavation will be backfilled and reinstated until a technique has been agreed. 

Monday 17th September

Excavate at the rear of The Tyne Pub and locate the 30” main for the purpose of extracting a dowel, to camera and video a section of water main. Gordon Mitchell has made contact with the owner of The Tyne Pub – Mr F Plater and agreed to maintain the parking area for the staff. This hole will be backfilled and reinstated immediately after the camera work.

Wednesday 19th September

Heaton Road – a road closure will be imposed between Denmark Street and Tynemouth Road. To allow Fastflow to excavate in the highway for the purpose of pipe inserting 100m x 225mm HPPE new water main.

Please Login in order to comment on this update.

View all updates
Work in your Community

Work in a business that supports your community

At Northumbrian Water, we work to make a difference in your community.

Have you considered a career that can help you do the same?

As well as the teams you see working in your streets, we have people doing a wide range of jobs that support that work to deliver the best possible water and sewerage services across the North East.

You can find out more about careers with Northumbrian Water and check out the latest vacancies by following the link below.

www.nwl.co.uk/careers