Update by Katie Burdon
24th September 18
Fastflow contacted the arborist (Lloyd Jones) reference Glasshouse Bridge. The arborist indicated that the trees are on a preservation order and any proposed works within the tree area must be formally applied for.
25th September 18
Heaton Road 12” main was isolated by Andrew Charleton
26th September 18
The customer event was held at the East End Pool by Amanda Hunt and Graeme Ridley (Northumbrian Water) with Gordon Mitchell, Gemma Crosby and Zena Alkadhily (Fastflow) from 15.00hrs – 19.00hrs
27th September 18
Fastflow surveyed the abandoned 30” main and ascertained that this was not suitable for pipe insert.
The excavation on Heaton Road is being prepared
28th September 18
A dowel was removed from the 12” main on Heaton Road initially to camera survey to try and locate the extent of the ductile iron main prior to pipe insert next week. The main is still being isolated and depressurised.
We visited the East End Pool with a gift to thank them for their hospitality at the customer event on Wednesday evening. (See attached photo)
29th September 18
Work will continue on Heaton Road with road closure in preparation for pipe inserting.