Update by Katie Burdon
Trunks Mains update
1st October 2018
Pipe insert 225mm HPPE is progressing on Heaton Road
We delivered a batch of food and clothes to Elim Church on Heaton Road (See attached photos)
2nd-3rd October 2018
Prepare pipe insert for chlorination procedure
4th-5th October 2018
Pressure test and chlorinate the new main on Heaton Road
7th October 2018
North Tyneside require weekend work on Sunday to remove x2 AV lids and frames and 1x valve lid and frame then backfill and reinstate. 3 & 4 way lights will be utilised.
Andrew Charleton is to mark up AV on Church Bank prior to works starting.
8th October 2018
Brick up 30” abandoned water main Glasshouse Bridge.
A sample will be taken from the new pipe on Heaton Road
9th – 10th October 2018
Heaton Road – Install 300v at junction of Denmark Street and connect 225mm to existing 12” main.
Connect new 225mm main up to the existing water main, 1 metre off the under pressure tee. This will be approximately 3 metres off the zone valve.
10th – 11th October 2018
Piece up 30” main on Glasshouse Bridge
11th October 2018
Start 90mm open cut on Corbridge Street
15th October 2018
Undertake trial hole on Glasshouse Bridge 12” main approximately half way between 12” valve and 30” main.
17th October 2018
NWL are to undertake a nightshift with loggers attached to 30” main to try and identify the position of leak.
16th-19th October 2018
Progress the 2x 90mm open cuts at the rear of Shields Road
Church Bank/Tynemouth Road - Fully complete on 7th October 2018
Heaton Road – Awaiting Sample results to undertake connections and install an extra 300v.
Denmark Street – 300v valve installation complete
Lobley Hill – A trial hole is required on 15” water main to progress work. There Is a chance there will be an opportunity to do this after the x2 open cuts at Shields Road.
Dalton Street – Pending work on Glasshouse Bridge being complete
Shields Road – Programmed to start on 7th January 2018
Please Login in order to comment on this update.