Update by Kevin McGargle
Good Afternoon
Just a brief update to confirm that yesterday we completed the final connection of our new pipework to the existing main within the estate, we are now today backfilling, surfacing and tidying the site, the machine & fencing etc will be removed tomorrow 17th january 2019 am before 10, all that remains is to final surface a section of path outside No.100 which will be done by our subcontractor in the next few days and seed the grass verge areas, this will be monitored over the next 3 months to ensure it takes to the standard it was before we arrived and can then be maintained by the grounds maintenance contractor for the estate thereafter.
I would like to thank everyone for their patience whilst we have been in this location.
Kind Regards
Kevin McGargle