Good Afternoon
Just a brief update to our works on Great Lime Road, we are currently progressing well with the installation of the new main despite challenges of unchartered utilities and stone penning under the existing road construction, we are now aiming to pressure test and chlorinate the main starting monday11th february 2019 which will involce about 4 days work, whilst this is ongoing we will be carrying out other reinstatement and connection works in order to complete this works phase as quick as we can.
Kind Regards
Kevin McGargle
Site Manager.