Just a brief update to our works on Great Lime Road as below:-
- Miller Close is now completed at the site entrance and permanently reinstated, The developer Taylor Wimpey is organising the white linining of the entrance in due course so please be vigilant for when this being carried out.
- Whiteley Road Holystone - we have re-commenced the installation of the linestop on the main, we anticipate works in this area to be complete as of wednesday next week.
- The next phase of work is located at the junction of Glebe road/ Great lime Road, this will commence on 28th March 2019 for a duration of 3 days.
Please also be aware that we have major works upcoming at the Roundabout of Southgate/ Great Lime Road on the 8th of April for 1 week and the roundabout of Whiteley Road/ Great Lime Road on the 15th April for 1 week.