WATER NETWORK IMPROVEMENT
CURRENT WEATHER
16°C

Tyneside Water Main Cleaning

Our water mains cleaning programme of works has been ongoing now for five years and to date, we have achieved 221km of cleaning works to our mains. There are a number of pipe sections that we still need to clean, with a total length of 9.0km. We are starting this work in August 2018 and anticipate completion in the Summer 2019.

Update by Katie Burdon

Portal update WC 2th April

 

Shields Road, Byker

Major works are ongoing with investigatory works.

 

West Road, Fenham

Fastflow are undertaking a trial hole x2 20” mains to enable the installation of a valve at a later date. This works is currently programmed for 10 days.

Robinson Street, Byker

Connections and service transfers are now compelte

 

Please Login in order to comment on this update.

View all updates
Work in your Community

Work in a business that supports your community

At Northumbrian Water, we work to make a difference in your community.

Have you considered a career that can help you do the same?

As well as the teams you see working in your streets, we have people doing a wide range of jobs that support that work to deliver the best possible water and sewerage services across the North East.

You can find out more about careers with Northumbrian Water and check out the latest vacancies by following the link below.

www.nwl.co.uk/careers