Tyneside Water Main Cleaning

Our water mains cleaning programme of works has been ongoing now for five years and to date, we have achieved 221km of cleaning works to our mains. There are a number of pipe sections that we still need to clean, with a total length of 9.0km. We are starting this work in August 2018 and anticipate completion in the Apri 2021.

Project updates

Update by Kevin McGargle

Good Afternoon

Just a quick update to the works at Bamburgh Road (Palmersville chippy) and the planned works going forward.

The Pressure Connections are now complete to the existing mains and we are now half way across the road installing a duct to sleeve the main through at a future date, we anticipate the works being completed in this area by Friday night for this visit, we will have to return in the future to install the new main through the grassed area.

Starting Next week west of Palmersville metro for 3 weeks we will be installing the next pahse of works, i have attached the advanced notice sign that has went out this morning on this, those affected at Kelvin Place and Roseberry Grange will have already received a direct letter drop through the door last Week.

I will update you further as the works proceed.

Kind Regards

Kevin McGargle

Site manager

Please Login in order to comment on this update.

Update by Katie Burdon

Portal Update WE 18.01.2019

 

Glasshouse Bridge

Northumbrian Water have drained off the 30” water main and Fastflow are continuing the excavations in the car park and grassed area.

Please Login in order to comment on this update.

Update by Kevin McGargle

Good Morning

Works have started today at Bamburgh Road (Palmersville Chippy) to install new connections to the water main in the footway opposite and to the rear in Young Road, the weather has took everyone by a bit of a surprise this morning but never the less we anticipate to be complete in the area by Friday 25th January 2019. We will then move back up to Palmersville Metro Station for 3 weeks but i will update you on this work nearer the time.

Kind Regards

Kevin McGargle

Site Manager

Please Login in order to comment on this update.

Update by Kevin McGargle

Good Afternoon

Just a brief update to confirm that yesterday we completed the final connection of our new pipework to the existing main within the estate, we are now today backfilling, surfacing and tidying the site, the machine & fencing etc will be removed tomorrow 17th january 2019 am before 10, all that remains is to final surface a section of path outside No.100 which will be done by our subcontractor in the next few days and seed the grass verge areas, this will be monitored over the next 3 months to ensure it takes to the standard it was before we arrived and can then be maintained by the grounds maintenance contractor for the estate thereafter.

I would like to thank everyone for their patience whilst we have been in this location.

Kind Regards

Kevin McGargle

Site Manager

Please Login in order to comment on this update.

Update by Kevin McGargle

Good Morning

Just a brief update on our works at Miller Close Killingworth, it may appear that we aern't doing much on site but rest assured we have been completing pressure testing and chlorination of the main that we have installed, we are now in a position to carry out tuesday next week the connection of the New main to the existing in the footway adjacent the layby, this will result in a loss of water supply from 9 am for a brief time, thereafter we will complete the bakfill and final reinstatement works to the area.

You will be card dropped on this by Northumbrian water's local workgroup.

Hope you have a great weekend.

Kind Regard's

Kevin McGargle - Site Manager

Please Login in order to comment on this update.

Update by Kevin McGargle

Happy New Year...

Just thought i'd provided a brief update, we have now recommenced the works at Miller Close Killingworth to expose the pipe ends ready for Chlorination and testing works next tuesday, once this is completed we will have to wait a period of a few days for the water sample results to be returned, we will be therefore looking to "tie in" this new pipework to the existing on Tuesday 15th January 2019 from 9am for a short window where the water supply will be turned off, cards will be posted by Northumbrian water in due course however we will keep you briefed on this nearer the time.

I trust you have had a great christmas and new year.

Kind Regards

Kevin McGargle - Site Manager

Please Login in order to comment on this update.

Update by Joan Tatters

Good Afternoon,

With the Christmas Holidays coming up, it’s time to share our final post of the year!
We would just like to thank all our lovely customers for their continued support and cooperation throughout the year to allow our projects across the region to run as smoothly and quickly as possible. Our sites will be shutting down on Friday 21st December and will re-open Thursday 3rd January. For anything urgent, you can contact the 24-hour Customer Contact Team at Northumbrian Water on 03457171100.
From all of us at MMB, we wish you all a Merry Christmas, and a very Happy New Year!

Please Login in order to comment on this update.

Update by Kevin McGargle

Good Morning, id just thought id give a brief overview of our works this week and into the New Year.

1. Miller Close killingworth - the new water main has been installed and the site backfilled and reinstated for the break, we do however have to return on the 3rd of January to chlorinate & test the new pipe to then complete the final connection works.

2. Ongoing trial holes at Salters lane Killingworth so that we can finalise some design work to be completed today and the TM removed .

3. Commence today a 2 day trial hole at Bamburgh Road Killingworth (opposite the chippy), this will determine the position of existing services in the area.

From the site team at MMB we would like to thank you for your patience whilst we are carrying out the works and would like to wish you and your family a merry christmas and happy new year.

Kind Regards

Kevin McGargle - Site Manager

Please Login in order to comment on this update.

Update by Katie Burdon

Portal update WE 14th December 2018

 

Lobley Hill Road

Festival Park Drive is now fully complete.

 

Glasshouse Bridge

Excavations in the Quayside Enterprise Centre carpark have now commenced.

Please Login in order to comment on this update.

Update by Katie Burdon

Portal update WE 7th December 2018

 

Monday 3rd December

Lobley Hill Road

Excavation was carried out at Swallowtail Drive to be able to undertake the 180mm connection

Wednesday 5th December 2018

Lobley Hill Road

The connection at Swallowtail Drive was undertaken at 9.30am

Shields Road

The connection on the 90mm open cut at Dalton Street was undertaken

Friday 7th December 2018

Glasshouse Bridge

The felling of the trees has commenced today in the grassed area on Glasshouse Bridge. This is being undertaken by an independent tree surgeon.

 

Please Login in order to comment on this update.

Work in your Community

Work in a business that supports your community

At Northumbrian Water, we work to make a difference in your community.

Have you considered a career that can help you do the same?

As well as the teams you see working in your streets, we have people doing a wide range of jobs that support that work to deliver the best possible water and sewerage services across the North East.

You can find out more about careers with Northumbrian Water and check out the latest vacancies by following the link below.

www.nwl.co.uk/careers