The construction phase of this project is now complete.

There may still be updates, so the project will remain here. We are still monitoring the project and will reply to any comments. So if you have any questions please feel free to comment or contact us here.

EEL PROTECTION SCHEME

Eels Regulations (2009) Compliance Project

We will be and are currently upgrading the following works to install new screens that are compliant with the Eels Regs 2009. Lumley WTW - (Works here are now complete), Blackwell RWPS - (Works here are now complete), Warkworth WTW - (we are also installing new pumps at the river water intake) , and Broken Scar WTW. The new screens will also improve the resilience of the works and protect the water supplies for our customers for many years to come

Update by Joan Tatters

Good Afternoon,

Just a quick update for you..........

The second pair of new screens will be lifted into position by the end of this month. They should be in operation (resilience testing) from mid-August, and be fully functional by early September ready for the start of leaf fall in Autumn............that should be job done!

Thank you for your co-operation once again

Please Login in order to comment on this update.

View all updates
Work in your Community

Work in a business that supports your community

At Northumbrian Water, we work to make a difference in your community.

Have you considered a career that can help you do the same?

As well as the teams you see working in your streets, we have people doing a wide range of jobs that support that work to deliver the best possible water and sewerage services across the North East.

You can find out more about careers with Northumbrian Water and check out the latest vacancies by following the link below.

www.nwl.co.uk/careers