Waren Mill

Construct new underground pumping station near centre of village. Install pumped rising main to reach new treatment lagoons approx’ 250m west of Budle Bay Campsite. Lay new gravity main discharging treated flows downhill past the new pumping station to a new Outfall near to the river mouth. Reconfigure other local sewers to re-direct flows to the new Pumping Station. Abandon the existing treatment works close to the Old Mill, make safe and tarmac over.

Start Date

April, 2018

Estimated End Date

November, 2018

Contractor

Mott MacDonald Bentley

Update by Joan Tatters

Good Afternoon Everyone,

I'm back from holiday now, so here is a brief up date:

Our work is steadily progressing and we are experiencing some challenging issues with the ground conditions. The rock strength within the shaft has exceeded our expectations and our experts believe the rock is almost three times the strength of concrete. "wow"

We will need to continue to blast the rock from the shaft and I can assure you it's proving to be a tough task, the site team will keep you informed of the timings.

On an environmental issue we will continue to use the removed rock to help to build and maintain the sea wall and use it for local repairs to the road in the area. By doing this we will minimise vehicle movement as we are almost keeping it in house here at Waren Mill.

In my absence there has been a lot of interest in the site by visitors and holiday makers, Andy and his team welcomed a family from Lewis and their 7 little boy was overwhelmed by the size of the digger plus two ex mechanical engineers who in their words were "nosey" and wanted to see extactly what was going on. Great stuff lads!

I will be visiting the site every Wednesday morning between 9 and 12.30 so come along and have a chat, I'd be happy to answer any questions you may have about the project.

It's good to be back, so keep logging on for updates..........oh, the new site notice board will also advertise the updates if you are out and about in the village

.

Please Login in order to comment on this update.

View all updates
Rate us

Rate us

We would love to hear your feed back on our community portal.

There was an error saving your answers. Please try again.

Saving your answers.
Please wait.

Your answers have been saved. Thankyou for giving us your feedback.

1. Do you feel that our Community Portal has helped to keep you informed about our work?

2. How likely is it that you would recommend our Community Portal to a friend or colleague?

3. How likely is it that you would recommend Northumbrian Water to a friend or colleague?

4. Do you have any suggestions to improve our Community Portal? Optional

Work in your Community

Work in a business that supports your community

At Northumbrian Water, we work to make a difference in your community.

Have you considered a career that can help you do the same?

As well as the teams you see working in your streets, we have people doing a wide range of jobs that support that work to deliver the best possible water and sewerage services across the North East.

You can find out more about careers with Northumbrian Water and check out the latest vacancies by following the link below.

www.nwl.co.uk/careers