Update by Joan Tatters
Good Morning Waren Mill
Great weather again today, a little cooler though.
My update for this week.........
The blastings in the trench are scheduled as follows, however as Andy and his team have said the rock and hard material in the pipe trench is proving to be a challenge so, the decision was made to blast rather than the continual hammering thus lessen the noise impact. (these blasts are no where near the magnitude of the previous shaft blasts).The first blasts took place yesterday and were very successful.
WEDNESDAY 8/08/2018 BLASTING 11.00AM to 5.00PM
THURSDAY 9/08/2018 BLASTING 11.00AM to 5.00PM
FRIDAY10/08/2018 BLASTING 11.00AM to 1.00PM
The team are currently reinstating the drainage trench by Budle Bay Caravan Park, this will release more road and pedestrian traffic. This is also great timing for the farmer opposite to harvest his field.
We are on target for commencing the work over the stream towards the Mill for Monday 13th as well.
Top Site
The earthworks are in full flow on the lagoon site and we are busy constructing the embankments.
I've attached some photos of both sites........oh and a cute little squirrel Andy rescued on the back road leading to the lagoons.