Update by Kevin McGargle
Good afternoon all
Just a brief update on the works at Whitton in Rothbury and the planned works ahead.
1. We are commencing the sinking of the new pumping station shaft at the main compound area on monday 10th August for the next 4 weeks, next week you will see an increase of vehicle movements in and out for this operation early in the week and at the back end of the week when we have concrete deliveries.
2. The works in Whitton village will be complete today in the field areas, we have tarmac reinstatement ongoing in Murray gardens to the trench in the highway to where we have been working in the field, we will still be present in this area for our compound facilities.
3. On Monday 10th August for the next 5 weeks we will be switching the road closure to cater for installing the new sewer in the highway on Silverton lane, please be mindful of the TM signage in the area.
i have attached a couple of photographs of interest.
Kind Regards
Kevin McGargle - Site Manager