Update by Ian Davison
Hi
Just a quick note to advise that our contractor Dunelm will be onsite next week excavating trial holes in the field between Whitton and Rothbury. The work is planned to commence on the 12th October and should be completed within a couple of days.
This is a geotechnical investigation which will allow the engineering team to assess the ground conditions within which the sewer diversion is proposed. Upon completion the land will be reinstated back to the original condition.
Thanks
Ian