Woodham Bridge Sewage Pumping Station

We are about to commence work to the sewage pumping station situated at the end of Windsor Close Newton Aycliffe refurbishing the station and replacing the pumps. This is part of a £2 million project of improvements in the network. Our normal hours are from 8am to 5pm Monday to Friday, if we need to work outside these hours we will let local residents know in advance

Update by Brian Hall

Good morning

We need to inform you about works scheduled to happen this week.

On Wednesday 19th September we will be commencing breaking out works at the site this will involve breaking up existing structures with power tools and may cause some noise.

We will do our best to reduce noise and disturbance; for example we will be using mechanical saws instead of jackhammers. Some noise may be noticeable but will be minimised as far as possible.

These works are scheduled to go on for 7 working days so should be complete by next Thursday.

We will continue to work 8-5 Monday to Friday during these works.

If you have any concern that you or anyone else in the area may be adversely affected by this please get in touch.

Thank you for your patience during this part of the works.

 

Please Login in order to comment on this update.

View all updates
Work in your Community

Work in a business that supports your community

At Northumbrian Water, we work to make a difference in your community.

Have you considered a career that can help you do the same?

As well as the teams you see working in your streets, we have people doing a wide range of jobs that support that work to deliver the best possible water and sewerage services across the North East.

You can find out more about careers with Northumbrian Water and check out the latest vacancies by following the link below.

www.nwl.co.uk/careers