Update by Joan Tatters
Good Morning,
Well last week was all stations go to be honest............
Treatment building: - The 2nd half of the slab was poured with 127m3 of concrete on Wednesday. The steel frame was erected on the Friday on the south side, its starting to take shape.
Contact tank: - Great collaborative work with our team and the subbies, between them they installed the cable conduit between the upstands on the roof, completed all the steelwork on the roof onThursday and all internal riser pipework and bellmouths in the channels.
Washwater Settlement Tank: - The shutters were placed for the wall stitches and pipework. On Thursday further concrete was poured to finish the tank for further shutter work Friday.
Access road:- All remaining kerbs were complete for the tarmac on Thursday/ Friday followed up by the white linning.
Well that was a week!
Please feel free to ask us any questions you may have, we would be happy to answer them.
Please Login in order to comment on this update.