Update by Joan Tatters
Good Afternoon,
Hope you are all keeping safe, here is the last update of 2020:-
Treatment building: -
The internal blockwork continues with the 2nd lift to the east side and the subcontractor has started installing the cable tray angle supports on the south side of the building.
Contact tank: -
Started the installation the pedestrian trackmats – 70% complete
Dechlorination chamber: -
Finished the installation on the tank and installed shutters for the walls. Poured the walls with 6.5m3 concrete
So, steady progress this week again, here are some photos of this weeks work. The team will be working up until 22nd then will make everything safe and secure and will leave for the festive break and return on January 4th 2021.
It's been a crazy year for us all, however, the team wish you all the very best of health and happiness for the new year and for those who celebrate Christmas, a Very Merry Christmas to you.