Update by Joan Tatters
Good Afternoon Folks,
Just been round the site with the Works Manager, it is impressive how things have progressed on in such a short time.
Treatment Building:-
Our subbie completed the MCC internal blockwork and stripped the scaffold then continued fixing the ceiling and replacement of the roof boards. They finished off the stud walling to the west of the welfare canteen, the painters started the first coat in the building and welfare area. The 1st fix plumbing and electrical has also been completed inside the welfare room and for the toilet block.
Althought the weather hasn't been too great, it hasn't hindered the progress of the project.
Today we have taken delivery of more site cabins to ensure our subbies and our team remain Covid safe, they are the new ones facing the B6525.